PRINCE2 Prince2-Foundation dumps

PRINCE2 Prince2-Foundation Exam Dumps

PRINCE2 7 Foundation written Exam
837 Reviews

Exam Code Prince2-Foundation
Exam Name PRINCE2 7 Foundation written Exam
Questions 296 Questions Answers With Explanation
Update Date December 01,2024
Price Was : $81 Today : $45 Was : $99 Today : $55 Was : $117 Today : $65

Genuine Exam Dumps For Prince2-Foundation:

Prepare Yourself Expertly for Prince2-Foundation Exam:

Our team of highly skilled and experienced professionals is dedicated to delivering up-to-date and precise study materials in PDF format to our customers. We deeply value both your time and financial investment, and we have spared no effort to provide you with the highest quality work. We ensure that our students consistently achieve a score of more than 95% in the PRINCE2 Prince2-Foundation exam. You provide only authentic and reliable study material. Our team of professionals is always working very keenly to keep the material updated. Hence, they communicate to the students quickly if there is any change in the Prince2-Foundation dumps file. The PRINCE2 Prince2-Foundation exam question answers and Prince2-Foundation dumps we offer are as genuine as studying the actual exam content.

24/7 Friendly Approach:

You can reach out to our agents at any time for guidance; we are available 24/7. Our agent will provide you information you need; you can ask them any questions you have. We are here to provide you with a complete study material file you need to pass your Prince2-Foundation exam with extraordinary marks.

Quality Exam Dumps for PRINCE2 Prince2-Foundation:

Pass4surexams provide trusted study material. If you want to meet a sweeping success in your exam you must sign up for the complete preparation at Pass4surexams and we will provide you with such genuine material that will help you succeed with distinction. Our experts work tirelessly for our customers, ensuring a seamless journey to passing the PRINCE2 Prince2-Foundation exam on the first attempt. We have already helped a lot of students to ace IT certification exams with our genuine Prince2-Foundation Exam Question Answers. Don't wait and join us today to collect your favorite certification exam study material and get your dream job quickly.

90 Days Free Updates for PRINCE2 Prince2-Foundation Exam Question Answers and Dumps:

Enroll with confidence at Pass4surexams, and not only will you access our comprehensive PRINCE2 Prince2-Foundation exam question answers and dumps, but you will also benefit from a remarkable offer – 90 days of free updates. In the dynamic landscape of certification exams, our commitment to your success doesn't waver. If there are any changes or updates to the PRINCE2 Prince2-Foundation exam content during the 90-day period, rest assured that our team will promptly notify you and provide the latest study materials, ensuring you are thoroughly prepared for success in your exam."

PRINCE2 Prince2-Foundation Real Exam Questions:

Quality is the heart of our service that's why we offer our students real exam questions with 100% passing assurance in the first attempt. Our Prince2-Foundation dumps PDF have been carved by the experienced experts exactly on the model of real exam question answers in which you are going to appear to get your certification.


PRINCE2 Prince2-Foundation Sample Questions

Question # 1

Which statement about the quality review technique is FALSE?

A. It enables a check to be made on a product's fitness for purpose
B. It defines the quality responsibilities of the project team 
C. It supports the management of future changes by providing a baseline for a product
D. It is used to gain wider acceptance of a product by involving key interested parties



Question # 2

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

A. quality
B. supplier
C. risk
D. product



Question # 3

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities

A. change budget
B. project budget
C. project's cost tolerance
D. project's risk tolerance 



Question # 4

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

A. Project Brief 
B. Project Initiation Documentation
C. Project mandate
D. Benefits Review Plan 



Question # 5

Which is part of quality control?

A. Undertake quality reviews
B. Write Product Descriptions
C. Provide assurance that the project is being conducted properly
D. Document the customer's quality expectations 



Question # 6

Identify the missing word in the following sentence. The guiding obligations and good practices that determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

A. Principles
B. Themes
C. Processes
D. Techniques 



Question # 7

Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity

A. Avoid
B. Reduce
C. Share
D. Transfer 



Question # 8

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

A. Configuration Item Record
B. Quality Register
C. Highlight Report
D. Checkpoint Report 



Question # 9

Which should be funded by a change budget?

A. Increase in agreed scope
B. Increase in agreed scope
C. Increase in agreed scope
D. Handover activities 



Question # 10

Which should be provided by corporate or program management before the Starting up a Project process commences?

A. A Project Brief
B. Sufficient information to identify the prospective Executive
C. The Project Initiation Documentation
D. Authority to initiate a project



Question # 11

Whose approval is needed to replace a Stage Plan with an Exception Plan?

A. Corporate or programme management
B. Project Board
C. Project Manager
D. Team Manager



Question # 12

What is an off-specification?

A. A new requirement
B. A quality tolerance
C. A type of issue
D. A major risk 



Question # 13

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

A. Benefits
B. Quality
C. Risk
D. Scope



Question # 14

Which is NOT one of the PRINCE2 integrated elements?

A. Tailoring PRINCE2 to the project environment
B. The processes
C. The products
D. The themes 



Question # 15

Which is the Issue Register NOT used for?

A. Capture external events that are impacting a stage
B. Record information about a deviation in stage tolerance
C. Capture any threats or opportunities that might have an impact on a stage
D. Record any problems identified when authorizing a Work Package



Question # 16

Which is a purpose of the Risk Register?

A. Describe the risk management techniques and standards to be applied to the project
B. Act as a central record of information relating to the identified risks for the project
C. Act as a repository for informal issues
D. List the responsibilities for achieving an effective risk management procedure 



Question # 17

Which is NOT considered when defining risk tolerance?

A. A Project Board's attitude towards risk-taking
B. The allocated risk budget
C. An organization's risk appetite
D. The amount of risk a Project Board considers acceptable 



Question # 18

Which process covers the work done by external suppliers who may NOT be using PRINCE2?

A. Closing a Project
B. Managing a Stage Boundary
C. Managing Product Delivery
D. Directing a Project



Question # 19

Which statement about the Directing a Project process is true?

A. Provides a mechanism for the Project Board to assure that there is a continued business justification
B. Covers the day-to-day activities of the Project Manager
C. Ensures there are regular progress meetings
D. Begins on completion of the Initiating a Project process 



Question # 20

How many management stages should a PRINCE2 project consist of?

A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
C. Initiation stage and at least one other management stage to cover the remainder of the project
D. Start up stage, initiation stage and a closing stage



PRINCE2 Prince2-Foundation Exam Reviews

Leave Your Review